EnergyAudit
Audits for energy utilities: EEG, CHP, concession fees, section 19 StromNEV
Your EEG and CHP final statement, section 19 StromNEV and concession fees: each statement with its own auditor’s report, planned back from its deadline.
KAV proof
Certificate
Section 19 StromNEV
Certificate
EEG and CHP final statement
Certificate
Spring is the bottleneck
Grid operators and utilities settle levies, subsidies and charges every year. Three deadlines fall between 31 March and 31 July, the fourth is set in the concession contract.
- 31 MarchCHP Act
- 31 MayEEG/CHP final statement
- 31 JulySection 19
- Date per contractConcession fees
If everything lands in spring, data preparation and audit compete for the same weeks.
One data basis, four certificates
- CHP Act auditsto BAFA and grid operator31 MarchIDW PH 9.970.34
- EEG and CHP final statementto the TSO31 MaySection 55 EnFG
- Grid charges s. 19to the TSO31 JulyIDW PH 9.970.30
- Concession fee statementto the municipalityper concession contractIDW PH 9.970.64, .67
Not every certificate is mandatory
- always
- EEG and CHP final statementfor aggregated final statementsSection 55(1) sent. 1 EnFG
- under conditions
- CHP Actplants above 2 MW while receiving surcharge paymentsSections 15(2), 30(1) no. 2 KWKG
- Section 19 StromNEVat the transmission system operator’s requestSection 19(2) sent. 15 StromNEV; IDW PH 9.970.30
- Concession fee statementto the municipality, audited where the concession contract requires itConcession contract; IDW PH 9.970.64, .67
- voluntary
- KAV proofsupplier proves to the grid operator, by audit certificate, that lower concession fees applySection 2(6) sent. 3 KAV
Where we audit in your settlement year
- Clarify dutiesWhich certificates are mandatory and which only on request.
- Plan backwardsFrom the deadlines 31 March, 31 May and 31 July.
- AuditEach statement on its own, once it is ready.
- SubmitTo the transmission system operator, BAFA or the municipality.
Who audits your certificates
- Registered audit firm, member of the IDW (opens in a new tab)Listed with the Chamber of Public Accountants. The German Public Accountant you talk to signs.
- Specialised in energy and sustainabilityAudits for the special equalisation scheme and carbon cost compensation. We developed a green electricity audit programme and audit the suppliers of ZF Friedrichshafen AG worldwide.
- Big Four backgroundWe learned auditing at Big Four firms, over ten years in financial statement and sustainability audits.
“We have had very good experiences working with justReporting. The audits were very thorough, reliable, fair and efficient.”
What utilities ask before certificate season
Who may audit CHP Act settlements?
German Public Accountants, audit firms, cooperative audit associations, sworn auditors and their firms.
Must the concession fee settlement with the municipality be audited?
Only where the concession contract provides for it. The KAV proof is separate: with it, the supplier proves to the grid operator, by audit certificate, that lower concession fees apply.
Which certificates are mandatory for grid operators?
The certificate on the combined EEG and CHP final statement is mandatory, submitted to the upstream TSO by 31 May (section 55(1) sent. 1 EnFG). Other final statements and notifications are certified by an auditor at the grid operator’s request (section 55(1) sent. 2 EnFG).
When is the section 19 StromNEV statement due?
Grid operators submit the annual statement of revenues lost through individual grid charges to the TSO by 31 July of the following year. The IDW audit guidance for it is IDW PH 9.970.30.
Does our CHP plant need a certificate?
Yes, above 2 MW of electrical CHP capacity, as long as it receives surcharge payments: the statement for the previous year goes audited to BAFA and the grid operator by 31 March. Up to 2 MW the data are due by 31 March without an audit (sections 15(2), (3) and 30 KWKG).
Do you also audit the utility’s annual accounts?
Yes. For grid operators and vertically integrated utilities the audit of the annual accounts also covers the unbundling accounts under section 6b(3) EnWG. If the municipality holds a majority, it can also request the audit under section 53 HGrG.
What does the certificate audit cost?
The fee depends on scope and effort. We give you the range after the intro call, and the fee is set out in writing in the engagement letter.
Intro call, 25 minutes
Your certificates in one schedule
Tell us your statements and dates. In the intro call we say what must be audited and what need not.
- Describe occasion and deadline
- Clarify what your occasion requires
- Learn scope, timeline and fee range
Helpful: your list of dates and last year’s certificates.

You always speak with a German Public Accountant who knows the field.Free of charge, no obligation, via Microsoft Teams.
Prefer email or phone?
A reply to every e-mail within 48 hours on working days. If it is urgent, say so and we will answer as soon as we can.
What else a utility needs
- Valuing utilities and grids
If a grid or shares in the utility must be valued.
- VSME reports
If the municipality, bank or customers ask for sustainability data.
- Special audits
If a utility is converted or merged.